Final site preparation is underway at the former IBM Endicott property, where five buildings were demolished.

THE IMPORTANT DETAILSAT A GLANCE ↓
Demolition project cost (per WNBF)
$8 million
Building space formerly on site (per WNBF)
About 550,000 square feet
Number of buildings demolished (per WNBF)
Five
Site size (per WNBF)
10 acres
Site preparation contractor (per WNBF)
LCP Group, Vestal
Original WNBF publication date
November 10, 2026

According to WNBF News, the Endicott site once occupied by five IBM buildings is being filled in nearly two years after an $8 million demolition project began. The buildings had about 550,000 square feet of space and were torn down over several months. WNBF reported that thousands of tons of asbestos-contaminated debris remained at the 10-acre site and were trucked to facilities in western New York because the Broome County landfill could not accept them. WNBF reported that crews from Vestal-based LCP Group are creating a level pad for future Huron Campus tenants. Broome County Executive Jason Garnar told WNBF that negotiations are ongoing and that he hopes to see movement on redevelopment in the next couple of months. Huron Campus representatives could not be reached for comment.

EXPLORE THE SOURCES

Go deeper.

This briefing brings together verified details from the reports below. Visit the original sources for additional coverage and context.

  1. 01IBM Endicott Demolition Site Prepped for RedevelopmentWNBF News Radio
See something we should correct or update? Send us a correction. Briefs may be revised as more facts become available.