SUNY Oneonta Battery Project Aims to Improve Campus Backup Power

NYPA and Urban Electric Power plan a $6.5 million battery demonstration at the Oneonta campus, according to WBNG.

THE IMPORTANT DETAILSAT A GLANCE ↓
Project Cost
$6.5 million
Battery System
Rechargeable zinc-manganese dioxide, 600 kilowatts of power, 3,600 kilowatt-hours of energy storage
Funding
NYPA and Urban Electric Power fund about $5.5 million; NYSERDA contributing nearly $1 million toward related costs
Manufacturing Timeline
Expected to begin early 2027
Construction Timeline
Anticipated in 2027; engineering work expected to begin late 2026
Campus Backup Claim
NYPA says the system could support critical campus buildings for more than six hours during an outage at reduced loads

According to a WBNG report published November 20, 2026, the New York Power Authority and battery manufacturer Urban Electric Power are moving forward with a $6.5 million project at SUNY Oneonta. The project would test a rechargeable battery system intended to provide backup electricity and reduce campus demand during peak periods. NYPA said the system could support critical campus buildings for more than six hours during an outage at reduced loads. Construction is anticipated in 2027, and engineering work is expected to begin in late 2026.

EXPLORE THE SOURCES

Go deeper.

This briefing brings together verified details from the reports below. Visit the original sources for additional coverage and context.